Bridge Project Near Upper Macungie Done Early

PennDot says bridge replacement in Lynn Township has been completed ahead of schedule.

 

PennDOT says a bridge project in Lynn Township, Lehigh County has been completed a month ahead of schedule. The township is northwest of Upper Macungie Township.

Donats Peak Road has been reopened following replacement of the structurally deficient Donats Peak Road Bridge over Ontelaunee Creek.

The project included drainage work, new guiderail, new roadway approaches and other miscellaneous construction.

During construction, Donats Peak Road was closed and detoured between PA
143 and Allemaengel Road.

The new bridge is a 91.5 feet long, 27.4 feet wide, concrete bulb T-beam
bridge.

Donats Peak Road has an average daily traffic volume of 143
vehicles.

Related Topics: penndot

Andrew

9:36 am on Tuesday, April 17, 2012

in Allentown the ward street bridge should be next ...it's only been a one lane for two long .... the areana downtown seems to taken proority

Reply
Comment_arrow
Patch_comments_icon

Susan Koomar

9:58 am on Tuesday, April 17, 2012

Thanks for your comment, Andrew. Anybody else have a bad bridge, construction delay or road project they want to talk about?

James Anthony

10:56 am on Tuesday, April 17, 2012

When will the work on Tilghman west of Blue Barn be completed?

Reply

Valerie Brosky

3:04 pm on Tuesday, April 17, 2012

James...Any Tilghman St questions are handled by the Community Relations Coordinator at 610-871-4555.

Reply

Leave a comment